Work Blank ______ structure is a plan that breaks down a project's goals into the many deliverables required to achieve it.
选项
A.spotlight
B.breakdown
C.creep
D.parking
查看解析
标准答案
Please login to view
思路分析
When tackling a question about terminology for project planning, each option needs careful evaluation.
Option 1: 'spotlight' — This word is commonly used to mean giving attention or emphasis, not a term for a project planning structure. It ......Login to view full explanation登录即可查看完整答案
我们收录了全球超50000道考试原题与详细解析,现在登录,立即获得答案。
类似问题
Question17 What is the main purpose of creating a work breakdown structure (WBS) in project management?Select one alternative: To identify and categorize all the risks and opportunities associated with project execution. To outline the sequence of tasks in the project and determine the critical path for completion. To identify missing stakeholders To break the project into smaller, manageable components that can be planned, tracked, and executed effectively. ResetMaximum marks: 2
Question17 What is the main purpose of creating a work breakdown structure (WBS) in project management?Select one alternative: To outline the sequence of tasks in the project and determine the critical path for completion. To break the project into smaller, manageable components that can be planned, tracked, and executed effectively. To identify and categorize all the risks and opportunities associated with project execution. To identify missing stakeholders ResetMaximum marks: 2
The team lists major deliverables, breaks them into smaller tasks, and assigns each to specific departments. Which project tool supports this process?
During the execution phase of a project, your team loses some key resources. There are a few deadlines to be met within the next three months and there are fortnightly update meetings with the client. A few new people are hired and you as the project manager need to set up a meeting to get the team working together on the project. What should be the main focus of this meeting?