Part 1Which is the best statement regarding work breakdown​ structure?Part 2 A. A packet is the smallest unit of work effort consuming both time and resources that the project manager can schedule and control. B. WBS should not include a task representing planning of the project that is being planned. C. Each activity in the WBS must have an​ "owner" who is responsible for doing the work. D. A Level 1 activity is a more micro view​ (greater level of​ detail) than a Level 2 activity.

选项
A.A. A packet is the smallest unit of work effort consuming both time and resources that the project manager can schedule and control.
B.B. WBS should not include a task representing planning of the project that is being planned.
C.C. Each activity in the WBS must have an ​ "owner" who is responsible for doing the work.
D.D. A Level 1 activity is a more micro view ​ (greater level of ​ detail) than a Level 2 activity.
查看解析

查看解析

标准答案
Please login to view
思路分析
In evaluating the statements about the work breakdown structure (WBS), I’ll consider what each option implies about standard PM practice and foundational concepts. Option A: 'A packet is the smallest unit of work effort consuming both time and resources that the project manager can schedule and control.' The term here is likely a misspelling of 'work package,' which is indeed the lowest level in a WBS. A work package is the smallest unit that can be scheduled, costed, and assigned, and it represents a discrete scope of work. This makes the statement largely c......Login to view full explanation

登录即可查看完整答案

我们收录了全球超50000道考试原题与详细解析,现在登录,立即获得答案。

类似问题

更多留学生实用工具

加入我们,立即解锁 海量真题独家解析,让复习快人一步!