题目
题目
单项选择题

Question3 According to the contract, your customer has assigned one of his staff to your project office to attend the meetings and contribute to the decision making. However, this person is too confrontational and his behavior to your project team members is intimidating. What should be your action in this situation?Select one alternative: Since the person is assigned by your client you don’t have any authority over him, so don’t do anything. Request to meet with the person about his behavior and its impact on the project. Also, inform the customer about the issue. Ask the customer to replace the person. You unilaterally decide to isolate the person and don’t let him in the project meetings. ResetMaximum marks: 2

选项
A.Since the person is assigned by your client you don’t have any authority over him, so don’t do anything.
B.Request to meet with the person about his behavior and its impact on the project. Also, inform the customer about the issue.
C.Ask the customer to replace the person.
D.You unilaterally decide to isolate the person and don’t let him in the project meetings.
查看解析

查看解析

标准答案
Please login to view
思路分析
The scenario involves a client-assigned staff member whose confrontational and intimidating behavior affects the project team. A thoughtful response should address behavior, maintain professional boundaries, and involve the client while preserving project integrity. Option 1: 'Since the person is assigned by your client you don’t have any authority over him, so don’t do anything.' This view wrongly assumes lack of authority eliminates responsibility. Even if the person i......Login to view full explanation

登录即可查看完整答案

我们收录了全球超50000道考试原题与详细解析,现在登录,立即获得答案。

类似问题

The general theme of sustainable business leadership is to consider _________ when making strategic decisions.

Question9 For the purpose of recording project lessons learned, you are analyzing the major delay in the project schedule. The root cause of the delay was a demonstration done by a group of green initiative supporters. They were unhappy because their representatives were not informed about all of the arrangements that you are taking to protect the environment. What could you and your team have done better to prevent this from happening?Select one alternative: A clearer communication management plan A more accurate stakeholder identification and engagement A more accurate risk response planning A better project management plan ResetMaximum marks: 1

Question3 According to the contract, your customer has assigned one of his staff to your project office to attend the meetings and contribute to the decision making. However, this person is too confrontational and his behavior to your project team members is intimidating. What should be your action in this situation?Select one alternative: Ask the customer to replace the person. Since the person is assigned by your client you don’t have any authority over him, so don’t do anything. You unilaterally decide to isolate the person and don’t let him in the project meetings. Request to meet with the person about his behavior and its impact on the project. Also, inform the customer about the issue. ResetMaximum marks: 2

Question1 You are a construction project manager and have been recently hired in a well known company as the manager of a highly crucial project. The project is expected to be completed in 2 years. During the project initiation phase you realize that some regulatory and environmental requirements have not been considered in the contract.Failure to meet the mentioned requirements will negatively affect your company’s reputation, but meeting them will require more time and cost, which will lead to budget and time overruns. In the latter case, there’s also a chance that the client decides to cancel the project. What would be your first action item in that situation?Select one alternative: As a seasoned construction project manager, contact the regulatory body to find out some workarounds for your project without telling other stakeholders. Since this is only a probability it does not need an immediate action. Just try to gather more information as the project goes ahead and decide later on. Ask client to send a scope change request that should be written immediately. Disclose your discovery to the project stakeholders including the client and solicit their viewpoints following by sending the change request if needed. ResetMaximum marks: 2

更多留学生实用工具

加入我们,立即解锁 海量真题独家解析,让复习快人一步!