题目
多项选择题
Which of the following statements are incorrect about risk management when dealing with plant and equipment in construction?
选项
A.Training and continuous education of the workforce on the latest safety protocols and the correct operation of machinery are integral components of an effective risk management program, aiming to reduce the likelihood of accidents and injuries.
B.Personal protective equipment (PPE) is the most effective measure and should always be prioritized over risk elimination, substitution, and engineering controls.
C.The hierarchical risk control model suggests starting with risk elimination, then exploring hazard substitution options. If risks persist, the model recommends moving to isolation and engineering controls before considering administrative strategies and personal protection measures.
D.Risk control measures should be formulated at the beginning of a project, often needless to account for reassessment of the developed strategies due to evolving worksite conditions. This approach helps with reducing cost in construction projects.
E.Risk management is an ongoing process that necessitates regular reassessment to accommodate new insights, technological advancements, and changes in project scope. This ensures that the implemented control measures remain effective over time.
F.Risk management strategies encompass creating an emergency response plan that anticipates potential accidents and delineates procedures to minimize their impact. This enhances on-site safety and preparedness.
查看解析
标准答案
Please login to view
思路分析
Here we analyze each statement to determine whether it is incorrect about risk management for plant and equipment in construction.
Option 1: 'Personal protective equipment (PPE) is the most effective measure and should always be prioritized over risk elimination, substitution, and engineering controls.' This is incorrect because the safety hierarchy of controls places PPE as the last line of defense, after eliminating hazards, substituting with safer alternatives, and applying engineering and administrative controls. Relying on PPE as the primary measure neglects the more effective, upstream controls and can give a false sense of security if other controls are not i......Login to view full explanation登录即可查看完整答案
我们收录了全球超50000道考试原题与详细解析,现在登录,立即获得答案。
类似问题
In engineering risk analysis, tolerable risks are
In engineering risk analysis, the risk owner will make the trade-off recommendation.
In a consumer society, many adults channel creativity into buying things
Economic stress and unpredictable times have resulted in a booming industry for self-help products
更多留学生实用工具
希望你的学习变得更简单
加入我们,立即解锁 海量真题 与 独家解析,让复习快人一步!