PMGT5887 (all) Weekly Quiz 7

单项选择题

You have overallocated a resource in Microsoft Project. Which feature allows you to adjust the workload distribution without changing the project end date?

选项
A.Baseline Reset
B.Work Breakdown Structure
C.Contour Adjustment
D.Resource Leveling
查看解析

查看解析

标准答案
Please login to view
思路分析
The question asks about adjusting workload distribution in Microsoft Project without altering the overall project end date when a resource is overallocated. Option 1: Baseline Reset. This would revert the project to its original baseline; it does not directly address the issue of redistributing workload or resolving overallocations, and it could affect the p......Login to view full explanation