What is the final outcome of the Requirement Specification process, which serves as a reference point for developers ?
选项
A.Project Management Plan
B.Use Case Diagram
C.Software Requirements Specification document
D.Functional Prototype

查看解析
标准答案
Please login to view
思路分析
The question asks: What is the final outcome of the Requirement Specification process, which serves as a reference point for developers?
Option 1: Project Management Plan. While the PM Plan governs how the project is executed, it does not represent the final requirements spe......Login to view full explanation登录即可查看完整答案
我们收录了全球超50000道考试原题与详细解析,现在登录,立即获得答案。
类似问题
A Requirements Specification states “The software shall show the weather for the next 24 hours”. The programmer delivers software that runs for 24 hours showing the current weather. However, what the user actually wanted was for it to show the weather forecast over the next 24 hours. What kind of computer failure is this?
Recording a system requirement for future use is called?
True or false: The software requirements specification is a document created by the vendor containing all the features and functionality of the software they need to create.
A specification for a new game is shown below.'The application must be multi-user and contain a timer and three levels'At which stage will such a specification be required?