PJM6015.20760.202525 PJM6015_Week 3_Test Your Knowledge (TYK)
单项选择题
In qualitative risk analysis, the project team sometimes uses a numeric scale and a color coding system assigning red, yellow and green to a pre-determined value range. This color coding system breaks the risks into groups requiring different level of attention. Green risks are those that (selected the best answer).
选项
A.Are of least concern
B.Can be ignored
C.Should be closely monitored
D.Require more attention
查看解析
标准答案
Please login to view
思路分析
In this question, we are evaluating what green risks signify in a qualitative risk analysis color-coding scheme that uses red, yellow, and green to categorize risk levels.
Option 1: 'Are of least concern' — This aligns with the common interpretation that green-coded risks are the lowest priority or least concerning, indic......Login to view full explanation登录即可查看完整答案
我们收录了全球超50000道考试原题与详细解析,现在登录,立即获得答案。
类似问题
Which risk characteristics are evaluated during the qualitative risk analysis?
ISO 31000 based risk analysis is
Anita is working with her team and SMEs to prioritize identified risks for further analysis. They decide to use a five-point scale of very low (VL), low (L), medium (M), high (H), and very high (VH) to assess the likelihood and impact of risk events. This process may be best described as
Which of the following tools and techniques are mostly recommended for qualitative risk analysis? (Select all that applies).