4510_PROJMGNT_1001UAC Quiz 2 - Case Study

单项选择题

The State Government is committing $593 million (AUD) in capital funding to the project. What project term describes the 250Mwe electrolyser, 200MW hydrogen fueled power plant and the Hydrogen storage facility?

选项
A.Project Scope
B.Project Risk
C.Project Managament Plan
D.Project Budget
查看解析

查看解析

标准答案
Please login to view
思路分析
The question presents a scenario where the State Government commits a substantial capital funding amount and asks which project term best describes the combination of a 250Mwe electrolyser, a 200MW hydrogen fueled power plant, and a Hydrogen storage facility. Option 1: 'Project Scope' — This term refers to the boundaries and deliverables of a proj......Login to view full explanation