题目
QANT_630-VA1-2025SP-VR Quiz 13 (Project Cost Management)
单项选择题
What is a minimum-cost schedule
查看解析
标准答案
Please login to view
思路分析
The question asks: 'What is a minimum-cost schedule'.
Option provided: 'A schedule created by reducing the project duration in a cost-effective manner'.
First, consider what a minimum-cost schedule typically means in project management; it usually refers to achieving the project goals while minimizing total cos......Login to view full explanation登录即可查看完整答案
我们收录了全球超50000道考试原题与详细解析,现在登录,立即获得答案。
类似问题
An activity with positive slack can be delayed without impacting the overall project completion time.
Assume that an activity can begin only after two other activities are completed. If the earliest completion time of one predecessor is twenty days, and the earliest completion time of the other predecessor is seventeen days, then the earliest start time of this activity must be twenty days.
Why do network diagrams typically precede Gantt charts in complex projects?
Question12 How can free float be used to shorten a project schedule?Select one alternative: By finishing the tasks with free floats sooner. By delaying the tasks with free float. By assigning free floats to the tasks in critical path to put the pressure off from resources. By reallocating resources from non-critical task with free float to the concurrent tasks in critical path. ResetMaximum marks: 2
更多留学生实用工具
希望你的学习变得更简单
加入我们,立即解锁 海量真题 与 独家解析,让复习快人一步!