题目
4510_CONMGNT_3008 Quiz 2
匹配题
Match each description with its corresponding term. 1: PERT 2: Gantt Chart 3: AOA 4: Time-Scaled Network Diagram 5: CPM 6: AON 7: Network Diagram 8: Timeline Chart 9: WBS 10: Milestone Chart
选项
A.Represents both activities and events
B.Task nodes indicate activities
C.Visualises overlapping tasks.
D.Utilises probability distribution.
E.Graphically represents project milestones.
F.Visually displays project milestones on a time axis.
G.Breaks down project deliverables.
H.Arrows symbolize activities.
I.Highlights task start and finish dates.
J.Prioritises task relationships.
查看解析
标准答案
Please login to view
思路分析
Question restatement: Match each description with its corresponding term.
Descriptions and intended matches:
1) Utilises probability distribution.
2) Visualises overlapping tasks.
3) Arrows symbolize activities.
4) Highlights task start and finish dates.
5) Prioritises task relationships.
6) Task nodes indicate activities.
7) Represents both activities and events
8) Visually displays project milestones on a time axis.
9) Breaks down project deliverables.
10) Graphically represents project milestones.
Option-by-option analysis:
Option 1: Rep Represents both activities and events → This description better fits a network diagram where both activities and events can be depicted, but it is specifically listed as an option rather than a standalone descriptive statement. If we consider standard chart types, PERT is known for its use of probability distributions to estimate activity durations, not for representing both activities and events. Therefore, the......Login to view full explanation登录即可查看完整答案
我们收录了全球超50000道考试原题与详细解析,现在登录,立即获得答案。
类似问题
An activity with positive slack can be delayed without impacting the overall project completion time.
Assume that an activity can begin only after two other activities are completed. If the earliest completion time of one predecessor is twenty days, and the earliest completion time of the other predecessor is seventeen days, then the earliest start time of this activity must be twenty days.
Why do network diagrams typically precede Gantt charts in complex projects?
Question12 How can free float be used to shorten a project schedule?Select one alternative: By finishing the tasks with free floats sooner. By delaying the tasks with free float. By assigning free floats to the tasks in critical path to put the pressure off from resources. By reallocating resources from non-critical task with free float to the concurrent tasks in critical path. ResetMaximum marks: 2