题目
题目

PMGT5205 - 2025S1 A1: Multiple Choice and Short Answer Quiz

单项选择题

Float or slack refers to:

选项
A.Ability to move human resources around as the scope of the project requires
B.Amount of time a schedule activity may be delayed from its early start without delaying the project finish date
C.Modification of a logical relationship that directs a delay in a successor task
D.Extra resources brought in to use in unanticipated circumstances
查看解析

查看解析

标准答案
Please login to view
思路分析
The question is asking: Float or slack refers to which concept in project scheduling? Option 1: 'Ability to move human resources around as the scope of the project requires' - This describes resource levelling or resource smoothing, not float/slack. It is about adjusting who does the work rather than delays in the ......Login to view full explanation

登录即可查看完整答案

我们收录了全球超50000道考试原题与详细解析,现在登录,立即获得答案。

类似问题

更多留学生实用工具

加入我们,立即解锁 海量真题独家解析,让复习快人一步!