PMGT5205 - 2025S1 A1: Multiple Choice and Short Answer Quiz
单项选择题
Float or slack refers to:
选项
A.Ability to move human resources around as the scope of the project requires
B.Amount of time a schedule activity may be delayed from its early start without delaying the project finish date
C.Modification of a logical relationship that directs a delay in a successor task
D.Extra resources brought in to use in unanticipated circumstances
查看解析
标准答案
Please login to view
思路分析
The question is asking: Float or slack refers to which concept in project scheduling?
Option 1: 'Ability to move human resources around as the scope of the project requires' - This describes resource levelling or resource smoothing, not float/slack. It is about adjusting who does the work rather than delays in the ......Login to view full explanation登录即可查看完整答案
我们收录了全球超50000道考试原题与详细解析,现在登录,立即获得答案。
类似问题
An activity with positive slack can be delayed without impacting the overall project completion time.
Assume that an activity can begin only after two other activities are completed. If the earliest completion time of one predecessor is twenty days, and the earliest completion time of the other predecessor is seventeen days, then the earliest start time of this activity must be twenty days.
Why do network diagrams typically precede Gantt charts in complex projects?
Question12 How can free float be used to shorten a project schedule?Select one alternative: By finishing the tasks with free floats sooner. By delaying the tasks with free float. By assigning free floats to the tasks in critical path to put the pressure off from resources. By reallocating resources from non-critical task with free float to the concurrent tasks in critical path. ResetMaximum marks: 2