题目
题目
单项选择题

Assume that an activity can begin only after two other activities are completed. If the earliest completion time of one predecessor is twenty days, and the earliest completion time of the other predecessor is seventeen days, then the earliest start time of this activity must be twenty days.

选项
A.True
B.False
查看解析

查看解析

标准答案
Please login to view
思路分析
In this scheduling scenario, an activity that can begin only after two predecessors is constrained by the later of the two finish times, because both must be completed before starting. Option True:......Login to view full explanation

登录即可查看完整答案

我们收录了全球超50000道考试原题与详细解析,现在登录,立即获得答案。

类似问题

更多留学生实用工具

加入我们,立即解锁 海量真题独家解析,让复习快人一步!