BU.300.620.51.FA25 Managing Complex Projects – Final Exam (35Q)

单项选择题

Why is 'starting with dates' instead of building a WBS first considered risky?

选项
A.It delays execution start
B.It hides real dependencies and logic under arbitrary deadlines
C.Dates reduce accountability for tasks
D.It inflates cost estimates by default
查看解析

查看解析

标准答案
Please login to view
思路分析
When you start with dates rather than a Work Breakdown Structure (WBS), the project planning dynamics shift in a few problematic ways. Option 1: 'It delays execution start' — While early dates might push activities, the core issue isn’t just delaying work; it’s that schedules built from dates can prematurely anchor work without understanding dependencies, making subsequent adjustment......Login to view full explanation