题目
单项选择题
A project Blank ______ is an individual who is an expert in project planning and management, defines and develops the project plan, and tracks the plan to ensure the project is completed on time and on budget.
选项
A.executive
B.agent
C.analyst
D.manager
查看解析
标准答案
Please login to view
思路分析
Examining the phrasing of the question, we are asked to identify the role described as an expert in project planning and management, who defines and develops the project plan and tracks it to ensure timely and on-budget completion.
Option 1: 'agent' — An agent typically represents someone else or handles tasks on behalf of an......Login to view full explanation登录即可查看完整答案
我们收录了全球超50000道考试原题与详细解析,现在登录,立即获得答案。
类似问题
A marketing company decides to launch a new integrated digital campaign for a major client. This involves developing new website content, creating social media assets, producing video testimonials, and coordinating efforts across their SEO, content, and social media teams. They have a clear brief from the client, a defined budget, and a timeline of four months. Once the campaign is delivered, the team members will return to their regular departmental duties or be assigned to new client projects. Which property best describes why this campaign launch is considered a project?
A project manager is leading a project to improve the efficiency of a manufacturing process using new software. By implementing this project successfully, the company expects to reduce waste and increase output. Which type of benefit, listed in the source as an outcome of effective project management, is the company anticipating from this project?
An IT project is established to develop a new internal reporting tool. Once the tool is successfully built, tested, and implemented, the project team is disbanded. This scenario illustrates which fundamental property of a project as defined in the source?
Which statement BEST captures the overall goal of managing complex projects?
更多留学生实用工具
希望你的学习变得更简单
加入我们,立即解锁 海量真题 与 独家解析,让复习快人一步!