单项选择题
A project portfolio is defined as ?
选项
A.A. Related projects, subsidiary programs, and program activities that are managed in a coordinated manner to obtain benefits not available from managing them individually.
B.B. Work that is recurring, ongoing, with no defined end.
C.C. A temporary endeavor that involves a series of structured tasks, activities, and deliverables to create a unique product, service, or result.
D.D. Projects, programs, subsidiary portfolios, and operations managed as a group to achieve strategic objectives.
查看解析
标准答案
Please login to view
思路分析
Let's examine each option in turn to see how well it fits the concept of a project portfolio.
Option A: 'Related projects, subsidiary programs, and program activities that are managed in a coordinated manner to obtain benefits not available from managing them individually.' This description sounds more like program management or a closely related concept, emphasizing coordination among related projects and programs to achieve benefits. However, it doesn't explicitly include all elements typically en......Login to view full explanation登录即可查看完整答案
我们收录了全球超50000道考试原题与详细解析,现在登录,立即获得答案。
类似问题
What is the role of the headquarters in the BCG matrix of corporate strategy?
In most companies, portfolio management is typically done at the SBU or ________ level of the firm.
Which of the following are components of portfolio management?
In a consumer society, many adults channel creativity into buying things
更多留学生实用工具
希望你的学习变得更简单
加入我们,立即解锁 海量真题 与 独家解析,让复习快人一步!