Centre for Engineering and Industrial Design Test - 2025

单项选择题

The Project Manager is creating an estimate for building a house. It is a house similar to what he builds often. He is using a figure of $2000 per square metre to calculate the estimate. What type of estimating is this?

查看解析

查看解析

标准答案
Please login to view
思路分析
The question describes the Project Manager creating an estimate for building a house using a constant rate of $2000 per square metre. This prompts us to identify the estimating approach being used. First, consider what parametric estimating involves: it applies a unit rate (a parameter) to a measurable attribute of the project to generate an overall estimate. In this case, the measurable attribute is the floor area in square metres, and the unit rate is $2000 pe......Login to view full explanation