Question at position 7 Match the following descriptions to the appropriate Material Requirements Planning component Prompt 1A specific order for a specific item and quantity to be released to the shop or to the supplierAnswer for prompt 1 A specific order for a specific item and quantity to be released to the shop or to the supplier[input]Prompt 2The number or quantity of each component or material needed to produce a single unit of the parent itemAnswer for prompt 2 The number or quantity of each component or material needed to produce a single unit of the parent item[input]Prompt 3The projected closing inventory at the end of a period. Calculated as the beginning inventory minus gross requirements, plus scheduled receipts, plus planned receipts from any planned order releases.Answer for prompt 3 The projected closing inventory at the end of a period. Calculated as the beginning inventory minus gross requirements, plus scheduled receipts, plus planned receipts from any planned order releases.[input]Prompt 4A planned order that can be frozen in quantity and time so that the MRP computer logic cannot automatically change it when conditions change.Answer for prompt 4 A planned order that can be frozen in quantity and time so that the MRP computer logic cannot automatically change it when conditions change.[input]Prompt 5Relates the gross requirements for a component part to the planned order releases of the parent item, so as to identify the source(s) of the item’s gross requirementsAnswer for prompt 5 Relates the gross requirements for a component part to the planned order releases of the parent item, so as to identify the source(s) of the item’s gross requirements[input]Possible answersTime BucketScheduled ReceiptPeggingLot SizeFirmed Planned OrderMRP ExplosionPlanned Order ReleaseNet RequirementPlanning FactorProject Available Inventory
选项
A.Time Bucket
B.Scheduled Receipt
C.Pegging
D.Lot Size
E.Firmed Planned Order
F.MRP Explosion
G.Planned Order Release
H.Net Requirement
I.Planning Factor
J.Project Available Inventory
查看解析
标准答案
Please login to view
思路分析
To tackle this matching task, I’ll go prompt by prompt and align each description with the most appropriate MRP component, then explain why the other options don’t fit.
Prompt 1: 'a specific order for a specific item and quantity to be released to the shop or to the supplier'
- Correct option: Planned Order Release. This term refers to the formally released plan indicating which orders should be issued to production or suppliers for a given item and quantity.
- Why the other options are incorrect here:
• Time Bucket: a time interval used for planning, not a specific order release itself.
• Scheduled Receipt: represents an inbound item arrival, not the instruction to release a new order.
• Pegging: a traceability concept linking requirements to their sources, not an order release.
• Lot Size: the quantity defined for a single order, but the prompt describes the release action, not the sizing rule.
• Firmed Planned Order: implies an order that is already fixed, which is a stronger......Login to view full explanation登录即可查看完整答案
我们收录了全球超50000道考试原题与详细解析,现在登录,立即获得答案。
类似问题
If a parent product requires 2 units of Component A, and MPS releases 200 parents, the gross requirement for Component A is:
If projected on-hand = ending inventory of last week + receipts – gross requirements, then a negative result means:
If a parent product requires 2 units of Component A, and MPS releases 200 parents, the gross requirement for Component A is:
If projected on-hand = ending inventory of last week + receipts – gross requirements, then a negative result means:
更多留学生实用工具
希望你的学习变得更简单
加入我们,立即解锁 海量真题 与 独家解析,让复习快人一步!