单项选择题
If projected on-hand = ending inventory of last week + receipts – gross requirements, then a negative result means:
选项
A.The Bill of Materials is incorrect
B.Master Production Schedule must be reduced
C.Excess inventory
D.A planned order is needed
查看解析
标准答案
Please login to view
思路分析
To approach this question, I’ll examine what a negative projection on-hand implies in the context of material requirements planning.
Option 1: The Bill of Materials is incorrect. While an incorrect BOM could lead to wrong material quantities, a negative projected on-hand specifically signals a shortage rel......Login to view full explanation登录即可查看完整答案
我们收录了全球超50000道考试原题与详细解析,现在登录,立即获得答案。
类似问题
If a parent product requires 2 units of Component A, and MPS releases 200 parents, the gross requirement for Component A is:
If a parent product requires 2 units of Component A, and MPS releases 200 parents, the gross requirement for Component A is:
If projected on-hand = ending inventory of last week + receipts – gross requirements, then a negative result means:
ERP in Production and Supply Chain Management[Fill in the blank] Explain how the Sales, Production and Procurement processes are integrated, identifying and explaining the integration points of each process.[Fill in the blank] Using the SAP S/4 HANA system for production planning and execution, explain the role of the Material Requirements Planning (MRP) system when creating a planned/production order. You must include in your explanation the MRP’s link with the material master data and its associated objects such as Bill of Materials, Work Centres and Routings.[Fill in the blank]
更多留学生实用工具
希望你的学习变得更简单
加入我们,立即解锁 海量真题 与 独家解析,让复习快人一步!