题目
MGS*3100*W10 25 Fall OM Exam 3 - Requires Respondus LockDown Browser
单项选择题
If a parent product requires 2 units of Component A, and MPS releases 200 parents, the gross requirement for Component A is:
选项
A.400
B.2
C.200
D.100
查看解析
标准答案
Please login to view
思路分析
We start by identifying what the gross requirement for a component means in this context: it is the total amount of Component A needed to fulfill the demand for all parent products.
Option 1: 100
- This would imply that the total gross requirement is 100 units of Co......Login to view full explanation登录即可查看完整答案
我们收录了全球超50000道考试原题与详细解析,现在登录,立即获得答案。
类似问题
If a parent product requires 2 units of Component A, and MPS releases 200 parents, the gross requirement for Component A is:
If projected on-hand = ending inventory of last week + receipts – gross requirements, then a negative result means:
If projected on-hand = ending inventory of last week + receipts – gross requirements, then a negative result means:
ERP in Production and Supply Chain Management[Fill in the blank] Explain how the Sales, Production and Procurement processes are integrated, identifying and explaining the integration points of each process.[Fill in the blank] Using the SAP S/4 HANA system for production planning and execution, explain the role of the Material Requirements Planning (MRP) system when creating a planned/production order. You must include in your explanation the MRP’s link with the material master data and its associated objects such as Bill of Materials, Work Centres and Routings.[Fill in the blank]
更多留学生实用工具
希望你的学习变得更简单
加入我们,立即解锁 海量真题 与 独家解析,让复习快人一步!