2258-1_20CM3034001 Exam

单项选择题

A contractor plans to fund early project cash flow using company reserves but has limited liquidity. Which risk should be recognized in the evaluation phase?

选项
A.Overstated bonding capacity
B.Delayed material submittals
C.Inaccurate cost estimates
D.Insufficient working capital for payroll and procurement
查看解析

查看解析

标准答案
Please login to view
思路分析
Question restatement: A contractor plans to fund early project cash flow using company reserves but has limited liquidity. Which risk should be recognized in the evaluation phase? Option 1: Overstated bonding capacity - This risk concerns the contractor's ability to obtain performance or payment bonds based on perceived capacity. While important, it focuses on bond limits rather than day-to-day liquidity for early cash needs. It is less directly tied to using reserves w......Login to view full explanation