A law office currently has five jobs to be scheduled, shown in the order in which they arrived.   Job Processing Time (hours) Due (hours) V 18 24 W 20 35 X 43 46 Y 27 35 Z 55 63   Calculate Average Flow Time (Total flow time/# of jobs), Average Lateness (Total lateness / # of jobs) and Average Number of Jobs (Total flow time / Total processing time) by sequencing the tasks using Shortest Processing Time rule. 

选项
A.AFT = 50, AL = 8, ANJ = 4.26
B.AFT = 8.5, AL = 4.26, ANJ = 1.96
C.AFT = 26.3, AL = 12, ANJ = 3.24
D.AFT = 78.4, AL = 39, ANJ = 2.405
E.AFT = 63.6, AL = 27.6, ANJ = 2.16
查看解析

查看解析

标准答案
Please login to view
思路分析
Question restated: A law office has five jobs V, W, X, Y, Z with processing times 18, 20, 43, 27, 55 hours and due dates 24, 35, 46, 35, 63 hours respectively. We are asked to compute Average Flow Time (AFT), Average Lateness (AL), and Average Number of Jobs (ANJ) after sequencing the tasks using the Shortest Processing Time (SPT) rule. Option list to evaluate: - AFT = 50, AL = 8, ANJ = 4.26 - AFT = 8.5, AL = 4.26, ANJ = 1.96 - AFT = 26.3, AL = 12, ANJ = 3.24 - AFT = 78.4, AL = 39, ANJ = 2.405 - AFT = 63.6, AL = 27.6, ANJ = 2.16 Step 1: Apply the Shortest Processing Time sequencing rule. Order jobs by processing time from smallest to largest: V (18), W (20), Y (27), X (43), Z (......Login to view full explanation

登录即可查看完整答案

我们收录了全球超50000道考试原题与详细解析,现在登录,立即获得答案。

更多留学生实用工具

加入我们,立即解锁 海量真题独家解析,让复习快人一步!