A Gantt workstation chart shows:
选项
A.The schedule of jobs assigned to specific workstations
B.The progress of each job through all work centers
C.The project budget and costs
D.The resource requirements per week
查看解析
标准答案
Please login to view
思路分析
Question restatement: A Gantt workstation chart shows:
Options:
- The resource requirements per week
- The progress of each job through all work centers
- The project budget and costs
- The schedule of jobs assigned to specific workstations
Option 1: 'The resource requirements per week' — This is more characteristic of a resource histogram or resource loading chart, not specifically a Gantt workstation chart. It focuses on quantities of resources ov......Login to view full explanation登录即可查看完整答案
我们收录了全球超50000道考试原题与详细解析,现在登录,立即获得答案。
类似问题
A small parts supplier has three orders waiting to be processed. The shop will begin work today (time = 0). Orders are scheduled using the First-Come, First-Served (FCFS) rule. What are the average days past due and the average flow time for these orders? Customer Time Since Order Arrived (days ago) Processing Time (days) Due Date (days from now) A 20 11 8 B 2 6 20 C 10 8 22
A law office currently has five jobs to be scheduled, shown in the order in which they arrived. Job Processing Time (hours) Due (hours) V 18 24 W 20 35 X 43 46 Y 27 35 Z 55 63 Calculate Average Flow Time (Total flow time/# of jobs), Average Lateness (Total lateness / # of jobs) and Average Number of Jobs (Total flow time / Total processing time) by sequencing the tasks using Shortest Processing Time rule.
Which one of the statements concerning sequencing rules is INCORRECT?
In a consumer society, many adults channel creativity into buying things
更多留学生实用工具
希望你的学习变得更简单
加入我们,立即解锁 海量真题 与 独家解析,让复习快人一步!