Question at position 2 You have just been hired as a senior financial manager of the XYZ Inc. by the eccentric CEO, Elon Tusk. Elon is considering the following potential projects (all cash flows happen at the end of the year). Assume the cost of capital for XYZ Inc. is 14%. [table] Year | Project A | Project B | Project C 0 | -200,000 | -480,000 | -680,000 1 | 150,000 | 280,000 | -100,000 2 | 80,000 | 280,000 | 350,000 3 | 90,000 | 280,000 | 350,000 4 | 100,000 | 280,000 | 750,000 5 | 110,000 | 280,000 | 650,000 [/table] What is the IRR for Project B?48.7%33.4%50.87%61.5%
选项
A.48.7%
B.33.4%
C.50.87%
D.61.5%
查看解析
标准答案
Please login to view
思路分析
We start by restating the problem: we need the IRR for Project B, where the cash flows (end of year) are: Year 0 = -480,000, and Years 1–5 each = 280,000. The IRR is the discount rate r that makes the net present value (NPV) zero: -480,000 + 280,000*(PV annuity factor for 5 years at rate r) = 0.
Option A: 48.7%. To assess this, compute the present value factor for 5 years at r = 0.487. The annuity factor (1 - (1+r)^-5)/r would be approximately (1 - 1/(1.487)^5)/0.487. Since (1.487)^5 is roughly 7......Login to view full explanation登录即可查看完整答案
我们收录了全球超50000道考试原题与详细解析,现在登录,立即获得答案。
类似问题
TB MC Qu. 09-51 Based on Lab 9-4 Excel Evaluating Investments Using... Based on Lab 9-4 Excel Evaluating Investments Using IRR, and given the results below, which investment should the company make if they use IRR to evaluate expected performance of each investment?
Question at position 2 (3 marks, difficulty level: Easy) What is the IRR of this project? [table] Year | Project A 0 | -380,000 1 | 180,000 2 | 280,000 3 | 280,000 4 | 280,000 5 | 80,000 [/table]48.86%53.33%52.29%54.38%
Question at position 2 (3 marks, difficulty level: Easy) What is the IRR of this project? [table] Year | Project A 0 | -380,000 1 | 180,000 2 | 280,000 3 | 280,000 4 | 280,000 5 | 80,000 [/table]54.38%52.29%53.33%48.86%
Question at position 2 (3 marks, difficulty level: Easy) What is the IRR of this project? [table] Year | Project A 0 | -380,000 1 | 180,000 2 | 280,000 3 | 280,000 4 | 280,000 5 | 80,000 [/table]48.86%52.29%54.38%53.33%
更多留学生实用工具
希望你的学习变得更简单
加入我们,立即解锁 海量真题 与 独家解析,让复习快人一步!