题目
4510_PROJMGNT_1001UAC Quiz 3 - Case Study
单项选择题
Which of the following tools would best help the project team to keep track of the schedule?
选项
A.Scope Statement
B.Quality Management Plan
C.Gannt chart
D.Schedule Performance Index
查看解析
标准答案
Please login to view
思路分析
To determine which tool best helps the project team keep track of the schedule, we should evaluate what each option primarily supports.
Option 1: Scope Statement. This document defines the project’s objectives, deliverables, and boundaries. While crucial for clarifying scope, it does not provide a mec......Login to view full explanation登录即可查看完整答案
我们收录了全球超50000道考试原题与详细解析,现在登录,立即获得答案。
类似问题
What is a simple bar chart that depicts project tasks against a calendar?
A Gantt workstation chart shows:
A(n) Blank ______ chart is a simple bar chart that lists project tasks vertically against the project’s time frame, listed horizontally.
What is a simple bar chart that lists project tasks vertically against the project’s time frame, listed horizontally?