What is a simple bar chart that depicts project tasks against a calendar?

选项
A.PERT Chart.
B.Work Breakdown Structure.
C.Gantt Chart.
D.Dependency.
查看解析

查看解析

标准答案
Please login to view
思路分析
Question focus: identifying the simple bar chart that shows project tasks plotted against a calendar. Option 1: PERT Chart. PERT charts are network diagrams that emphasize task sequence and dependencies, usually with nodes and arrows, not a calendar-aligned bar presentation. This......Login to view full explanation