3600 Final Exam- Requires Respondus LockDown Browser
单项选择题
Your team estimates that a new feature will take 3 weeks based on similar past projects. However, halfway through, a key dependency is delayed, and integration takes an extra two weeks. Your manager asks why the estimate was so far off. What was most likely missing from the team’s estimation process?
选项
A.Planning poker
B.Accurate story points
C.A Gantt chart
D.Developer time tracking
E.Buffering for uncertainty and external risk
查看解析
标准答案
Please login to view
思路分析
The scenario describes a project estimate that was later invalidated by an outside factor—a key dependency delaying and pushing integration by two weeks. This points to a gap in anticipating uncertainty and external risks rather than purely internal planning accuracy.
Option 1: 'Planning poker' — Planning poker is a collaborative estimation technique used to assign effort or size......Login to view full explanation登录即可查看完整答案
我们收录了全球超50000道考试原题与详细解析,现在登录,立即获得答案。
类似问题
In a consumer society, many adults channel creativity into buying things
Economic stress and unpredictable times have resulted in a booming industry for self-help products
People born without creativity never can develop it
A product has a selling price of $20, a contribution margin ratio of 40% and fixed cost of $120,000. To make a profit of $30,000. The number of units that must be sold is: Type the number without $ and a comma. Eg: 20000
更多留学生实用工具
希望你的学习变得更简单
加入我们,立即解锁 海量真题 与 独家解析,让复习快人一步!