题目
BU.300.620.51.FA25 Managing Complex Projects – Final Exam (35Q)
单项选择题
Why can CPI alone give a misleading picture of project health?
选项
A.It ignores schedule pressure and timing of work
B.It ignores scope
C.It ignores cost performance
D.It changes over time
查看解析
标准答案
Please login to view
思路分析
Consider what CPI is and what it measures in project control.
Option 1: 'It ignores schedule pressure and timing of work' — this is true. CPI calculates cost performance by comparing earned value to actual cost, focusing on cost efficiency, not on when work is performed or......Login to view full explanation登录即可查看完整答案
我们收录了全球超50000道考试原题与详细解析,现在登录,立即获得答案。
类似问题
Given CPI < 1 and SPI < 1, and schedule pressure is causing overtime, which EAC formula is MOST realistic?
At Month 4 of a project, PV = $1.2M, EV = $0.95M, and AC = $1.10M. Which interpretation is correct?
Earned Value results show CPI < 1 and SPI < 1. Which conclusion is MOST accurate?
Question5 As the project manager you are reviewing the earned value analysis (EVA) report performed by your team. The Schedule Performance Index (SPI) is 0.87. What does this figure mean to you?Select one alternative: The project is getting 87 cents out of each dollar spent. You are ahead of schedule. Your project is running according to the budget. The progress of your project is only 87% of what it is planned, so you are behind the schedule. ResetMaximum marks: 2