题目
题目
单项选择题

Question5 As the project manager you are reviewing the earned value analysis (EVA) report performed by your team. The Schedule Performance Index (SPI) is 0.87. What does this figure mean to you?Select one alternative: The project is getting 87 cents out of each dollar spent. Your project is running according to the budget. You are ahead of schedule. The progress of your project is only 87% of what it is planned, so you are behind the schedule. ResetMaximum marks: 2

选项
A.The project is getting 87 cents out of each dollar spent.
B.Your project is running according to the budget.
C.You are ahead of schedule.
D.The progress of your project is only 87% of what it is planned, so you are behind the schedule.
查看解析

查看解析

标准答案
Please login to view
思路分析
To interpret the Schedule Performance Index (SPI), we recall that SPI = EV / PV, where EV is earned value and PV is planned value. An SPI of 1.0 indicates schedule performance exactly as planned. Values below 1.0 mean the project is progressing more slowly than planned, while values above 1.0 indicate ahead-of-schedule performance. Option 1......Login to view full explanation

登录即可查看完整答案

我们收录了全球超50000道考试原题与详细解析,现在登录,立即获得答案。

类似问题

更多留学生实用工具

加入我们,立即解锁 海量真题独家解析,让复习快人一步!