题目
CVEN9731 Project Management Framework - 2025 T3
单项选择题
A project has a total budget of $800,000 and is planned to be completed in 12 months. After 5 months, half of the budget is spent, and the following data is provided:Planned Value (PV) = $350,000 Earned Value (EV) = $250,000 Remaining Work requires an efficiency factor of 0.9 on the current performance Given this information, calculate the Estimate at Completion (EAC) using the following formula for atypical conditions:EAC=AC+BAC−EVCPI×Efficiency FactorEAC = AC + \frac{BAC - EV}{CPI \times Efficiency \ Factor}

查看解析
标准答案
Please login to view
思路分析
We start by restating the given data and identifying the key variables to compute EAC under atypical conditions.
- Total Budget (BAC) = 800,000
- Planned Value (PV) after 5 months = 350,000
- Earned Value (EV) after 5 months = 250,000
- Amount spent so far (Actual Cost, AC) = since half the budget is spent in 5 months, AC = 800,000 / 2 = 400,000
- Remaining Work requires an efficiency factor of 0.9 on current performance
- CPI (Cost Performance Index) = EV / AC = 250,000 / 400,000 = 0.625
- BAC......Login to view full explanation登录即可查看完整答案
我们收录了全球超50000道考试原题与详细解析,现在登录,立即获得答案。
类似问题
Why can CPI alone give a misleading picture of project health?
Given CPI < 1 and SPI < 1, and schedule pressure is causing overtime, which EAC formula is MOST realistic?
At Month 4 of a project, PV = $1.2M, EV = $0.95M, and AC = $1.10M. Which interpretation is correct?
Earned Value results show CPI < 1 and SPI < 1. Which conclusion is MOST accurate?