A project has a total budget of $800,000 and is planned to be completed in 12 months. After 5 months, half of the budget is spent, and the following data is provided:Planned Value (PV) = $350,000 Earned Value (EV) = $250,000 Remaining Work requires an efficiency factor of 0.9 on the current performance Given this information, calculate the Estimate at Completion (EAC) using the following formula for atypical conditions:EAC=AC+BAC−EVCPI×Efficiency FactorEAC = AC + \frac{BAC - EV}{CPI \times Efficiency \ Factor}

题目图片
查看解析

查看解析

标准答案
Please login to view
思路分析
We start by restating the given data and identifying the key variables to compute EAC under atypical conditions. - Total Budget (BAC) = 800,000 - Planned Value (PV) after 5 months = 350,000 - Earned Value (EV) after 5 months = 250,000 - Amount spent so far (Actual Cost, AC) = since half the budget is spent in 5 months, AC = 800,000 / 2 = 400,000 - Remaining Work requires an efficiency factor of 0.9 on current performance - CPI (Cost Performance Index) = EV / AC = 250,000 / 400,000 = 0.625 - BAC......Login to view full explanation

登录即可查看完整答案

我们收录了全球超50000道考试原题与详细解析,现在登录,立即获得答案。

类似问题

更多留学生实用工具

加入我们,立即解锁 海量真题独家解析,让复习快人一步!