题目
题目

BU.300.620.51.FA25 Managing Complex Projects – Final Exam (35Q)

单项选择题

At Month 4 of a project, PV = $1.2M, EV = $0.95M, and AC = $1.10M. Which interpretation is correct?

选项
A.Over budget, behind schedule
B.Under budget, ahead of schedule
C.Over budget, ahead of schedule
D.On budget, behind schedule
查看解析

查看解析

标准答案
Please login to view
思路分析
First, let’s compute the key Earned Value Management indicators to interpret the project status. The Cost Variance (CV) = EV − AC = 0.95 − 1.10 = −0.15 million, which is negative and indicates the project is spending more than earned value, i.e., over budget. Next, Schedule Variance (SV) = EV − PV = 0.95 − 1.20 = −0.25 million, which is also negative, meaning......Login to view full explanation

登录即可查看完整答案

我们收录了全球超50000道考试原题与详细解析,现在登录,立即获得答案。

类似问题

更多留学生实用工具

加入我们,立即解锁 海量真题独家解析,让复习快人一步!