题目
CVEN9731 Project Management Framework - 2025 T3
单项选择题
You are managing a project with a one-year duration and a budget at completion (BAC) of $ 100,000. After 6 months, the project is 40% complete and the actual cost (AC) is $40,000. Consider a linear project progress inn this case. Which one of the following statements is correct?

查看解析
标准答案
Please login to view
思路分析
Start by identifying the key values and applying earned value concepts. EV (earned value) = percent complete × BAC = 0.40 × 100,000 = 40,000. AC (actual cost) = 40,000. PV (planned value) at 6 months for a linear, one-year project = (6/12) × BAC = 0.5 × 100,000 = 50,000.
Option a: 'The project is behind the schedule ......Login to view full explanation登录即可查看完整答案
我们收录了全球超50000道考试原题与详细解析,现在登录,立即获得答案。
类似问题
Why can CPI alone give a misleading picture of project health?
Given CPI < 1 and SPI < 1, and schedule pressure is causing overtime, which EAC formula is MOST realistic?
At Month 4 of a project, PV = $1.2M, EV = $0.95M, and AC = $1.10M. Which interpretation is correct?
Earned Value results show CPI < 1 and SPI < 1. Which conclusion is MOST accurate?
更多留学生实用工具
希望你的学习变得更简单
加入我们,立即解锁 海量真题 与 独家解析,让复习快人一步!