BU.300.620.51.FA25 Managing Complex Projects – Final Exam (35Q)

单项选择题

Earned Value results show CPI < 1 and SPI < 1. Which conclusion is MOST accurate?

选项
A.Ahead of schedule but over budget
B.Performance cannot be assessed
C.Behind schedule and over budget
D.Over budget but efficient
查看解析

查看解析

标准答案
Please login to view
思路分析
To tackle this question, I’ll evaluate what CPI and SPI indicate in Earned Value Management and then test each answer choice against those indicators. Option 1: 'Ahead of schedule but over budget' would require SPI > 1 (better schedule performance) and CPI < 1 (cost overrun). Since the question states both CP......Login to view full explanation