BU.300.620.51.FA25 Managing Complex Projects – Final Exam (35Q)
单项选择题
Given CPI < 1 and SPI < 1, and schedule pressure is causing overtime, which EAC formula is MOST realistic?
选项
A.EAC = BAC / CPI
B.EAC = AC + (BAC − EV) / CPI
C.EAC = AC + (BAC − EV) / (CPI × SPI)
D.EAC = EV + AC − PV
查看解析
标准答案
Please login to view
思路分析
Topic context: Earned Value Management (EVM) in project scheduling and cost forecasting. The question asks which EAC (Estimate at Completion) formula is MOST realistic given CPI < 1 and SPI < 1, with schedule pressure causing overtime.
Option A: 'EAC = BAC / CPI' — This formula isolates cost performance factor only, duplicating consideration of CPI but ignoring schedule performance (SPI) and work scope progression. If SPI is < 1, more work remains than earned value would indicate, so using only CPI would under-adjust the completi......Login to view full explanation登录即可查看完整答案
我们收录了全球超50000道考试原题与详细解析,现在登录,立即获得答案。
类似问题
Why can CPI alone give a misleading picture of project health?
At Month 4 of a project, PV = $1.2M, EV = $0.95M, and AC = $1.10M. Which interpretation is correct?
Earned Value results show CPI < 1 and SPI < 1. Which conclusion is MOST accurate?
Question5 As the project manager you are reviewing the earned value analysis (EVA) report performed by your team. The Schedule Performance Index (SPI) is 0.87. What does this figure mean to you?Select one alternative: The project is getting 87 cents out of each dollar spent. You are ahead of schedule. Your project is running according to the budget. The progress of your project is only 87% of what it is planned, so you are behind the schedule. ResetMaximum marks: 2