BU.300.620.51.FA25 Managing Complex Projects – Final Exam (35Q)

单项选择题

Given CPI < 1 and SPI < 1, and schedule pressure is causing overtime, which EAC formula is MOST realistic?

选项
A.EAC = BAC / CPI
B.EAC = AC + (BAC − EV) / CPI
C.EAC = AC + (BAC − EV) / (CPI × SPI)
D.EAC = EV + AC − PV
查看解析

查看解析

标准答案
Please login to view
思路分析
Topic context: Earned Value Management (EVM) in project scheduling and cost forecasting. The question asks which EAC (Estimate at Completion) formula is MOST realistic given CPI < 1 and SPI < 1, with schedule pressure causing overtime. Option A: 'EAC = BAC / CPI' — This formula isolates cost performance factor only, duplicating consideration of CPI but ignoring schedule performance (SPI) and work scope progression. If SPI is < 1, more work remains than earned value would indicate, so using only CPI would under-adjust the completi......Login to view full explanation