题目
PMGT5889 (NE) Online Quiz
匹配题
Your project status can be presented with the following diagram: Match the values presented in this graph with the corresponding Earned Value Analysis indicators. Formulas: EVA Component Formula Planned value (PV) N/A Earned value (EV) N/A Actual cost (AC) N/A Budget at completion (BAC) N/A Schedule variance (SV) SV = EV – PV Cost variance (CV) CV = EV- AC Estimated final duration PlannedProjectDuration / SPI % Complete %Complete = (EV/BAC) x 100 Schedule performance index (SPI) SPI = EV/PV Cost performance index (CPI) CPI = EV/AC Estimate at completion (EAC) – final cost Future work will be accomplished at the planned rate: Both CPI and SPI influence the remaining work: CPI is expected to be the same for the remainder of the project: EAC = AC + BAC – EV EAC = AC + [(BAC-EV)/(CPIxSPI)] EAC = BAC/CPI Estimate to complete (ETC) ETC = EAC – AC Variance at Completion (VAC) VAC = BAC-EAC 1: Actual Cost (AC) 2: Planned Value (PV) 3: Earned Value (EV) 4: Original Budget (BAC) 5: Schedule Performance Index (SPI) 6: Cost Performance Index (CPI) 7: Schedule Variance (SV) - money 8: Cost Variance (CV) 9: Project duration (months) 10: Months that project is behind/ahead of schedule at the moment
选项
A.0.94
B.$15M
C.$1M
D.$17M
E.-$1M
F.21
G.$23M
H.1.07
I.$16M
J.1
查看解析
标准答案
Please login to view
思路分析
The task presents a matching exercise for Earned Value Analysis (EVA) indicators and a set of values to fit each indicator. I’ll go through each answer option and explain what it would mean if that value were assigned to a given EVA metric, referencing the standard EVA formulas where relevant.
Option analysis by value:
- 0.94
- Possible interpretation: This aligns with the Schedule Performance Index (SPI) when EV and PV are 15 and 16 respectively, since SPI = EV/PV. A value of 0.94 would indicate the project is behind schedule on a relative, index basis. This is a plausible match for SPI, given typical EV data, but it would not be the numerical value for VARs such as SV or CV, which are currency-based.
- $15M
- This is a currency amount. In EVA terms, this value most naturally represents Earned Value (EV) if EV is the amount of work actually completed expressed in budget terms. It would be unlikely to be PV, AC, or BAC unless the project’s plotted data align, but EV = $15M is perfectly reasonable as a standalone value for......Login to view full explanation登录即可查看完整答案
我们收录了全球超50000道考试原题与详细解析,现在登录,立即获得答案。
类似问题
Your project status can be presented with the diagram: What is the status of your project? Formulas: EVA Component Formula Planned value (PV) N/A Earned value (EV) N/A Actual cost (AC) N/A Budget at completion (BAC) N/A Schedule variance (SV) SV = EV – PV Cost variance (CV) CV = EV- AC Estimated final duration PlannedProjectDuration / SPI % Complete %Complete = (EV/BAC) x 100 Schedule performance index (SPI) SPI = EV/PV Cost performance index (CPI) CPI = EV/AC Estimate at completion (EAC) – final cost Future work will be accomplished at the planned rate: Both CPI and SPI influence the remaining work: CPI is expected to be the same for the remainder of the project: EAC = AC + BAC – EV EAC = AC + [(BAC-EV)/(CPIxSPI)] EAC = BAC/CPI Estimate to complete (ETC) ETC = EAC – AC Variance at Completion (VAC) VAC = BAC-EAC
Your project status can be presented with the following diagram: Match the values presented in this graph with the corresponding Earned Value Analysis indicators. Formulas: EVA Component Formula Planned value (PV) N/A Earned value (EV) N/A Actual cost (AC) N/A Budget at completion (BAC) N/A Schedule variance (SV) SV = EV – PV Cost variance (CV) CV = EV- AC Estimated final duration PlannedProjectDuration / SPI % Complete %Complete = (EV/BAC) x 100 Schedule performance index (SPI) SPI = EV/PV Cost performance index (CPI) CPI = EV/AC Estimate at completion (EAC) – final cost Future work will be accomplished at the planned rate: Both CPI and SPI influence the remaining work: CPI is expected to be the same for the remainder of the project: EAC = AC + BAC – EV EAC = AC + [(BAC-EV)/(CPIxSPI)] EAC = BAC/CPI Estimate to complete (ETC) ETC = EAC – AC Variance at Completion (VAC) VAC = BAC-EAC 1: Actual Cost (AC) 2: Planned Value (PV) 3: Earned Value (EV) 4: Original Budget (BAC) 5: Schedule Performance Index (SPI) 6: Cost Performance Index (CPI) 7: Schedule Variance (SV) - money 8: Cost Variance (CV) 9: Project duration (months) 10: Months that project is behind/ahead of schedule at the moment
In a consumer society, many adults channel creativity into buying things
Economic stress and unpredictable times have resulted in a booming industry for self-help products
更多留学生实用工具
希望你的学习变得更简单
加入我们,立即解锁 海量真题 与 独家解析,让复习快人一步!