题目
题目

PMGT5889 (NE) Practice Quiz

匹配题

Your project status can be presented with the following diagram: Match the values presented in this graph with the corresponding Earned Value Analysis indicators. Formulas: EVA Component Formula Planned value (PV) N/A Earned value (EV) N/A Actual cost (AC) N/A Budget at completion (BAC) N/A Schedule variance (SV) SV = EV – PV Cost variance (CV) CV = EV- AC Estimated final duration PlannedProjectDuration / SPI % Complete %Complete = (EV/BAC) x 100 Schedule performance index (SPI) SPI  = EV/PV Cost performance index (CPI) CPI = EV/AC Estimate at completion (EAC) – final cost Future work will be accomplished at the planned rate: Both CPI and SPI influence the remaining work: CPI is expected to be the same for the remainder of the project:   EAC = AC + BAC – EV  EAC = AC + [(BAC-EV)/(CPIxSPI)]  EAC = BAC/CPI Estimate to complete (ETC) ETC = EAC – AC Variance at Completion (VAC) VAC = BAC-EAC 1: Actual Cost (AC) 2: Planned Value (PV) 3: Earned Value (EV) 4: Original Budget (BAC) 5: Schedule Performance Index (SPI) 6: Cost Performance Index (CPI) 7: Schedule Variance (SV) - money 8: Cost Variance (CV) 9: Project duration (months) 10: Months that project is behind/ahead of schedule at the moment

题目图片
查看解析

查看解析

标准答案
Please login to view
思路分析
The question asks you to match each EVA indicator to the value shown in the graph. I’ll walk through each provided option in turn, explaining what it represents and whether the value fits the corresponding EVA metric. Option 1: "$13M" for Planned Value (PV). - PV represents the planned cost of the work scheduled to be completed by a given date. In the data shown, PV is $13M, so this match is correct for PV. - Misconception to watch for: PV is not the same as EV or AC; PV is the baseline plan, not actual performance. Option 2: "$13M" for Earned Value (EV). - EV is the value of work actually performed, measured in budgeted dollars. Here EV is given as $12M, not $13M, so a match of $13M ......Login to view full explanation

登录即可查看完整答案

我们收录了全球超50000道考试原题与详细解析,现在登录,立即获得答案。

类似问题

Your project status can be presented with the following diagram: Match the values presented in this graph with the corresponding Earned Value Analysis indicators. Formulas: EVA Component Formula Planned value (PV) N/A Earned value (EV) N/A Actual cost (AC) N/A Budget at completion (BAC) N/A Schedule variance (SV) SV = EV – PV Cost variance (CV) CV = EV- AC Estimated final duration PlannedProjectDuration / SPI % Complete %Complete = (EV/BAC) x 100 Schedule performance index (SPI) SPI  = EV/PV Cost performance index (CPI) CPI = EV/AC Estimate at completion (EAC) – final cost Future work will be accomplished at the planned rate: Both CPI and SPI influence the remaining work: CPI is expected to be the same for the remainder of the project:   EAC = AC + BAC – EV  EAC = AC + [(BAC-EV)/(CPIxSPI)]  EAC = BAC/CPI Estimate to complete (ETC) ETC = EAC – AC Variance at Completion (VAC) VAC = BAC-EAC 1: Actual Cost (AC) 2: Planned Value (PV) 3: Earned Value (EV) 4: Original Budget (BAC) 5: Schedule Performance Index (SPI) 6: Cost Performance Index (CPI) 7: Schedule Variance (SV) - money 8: Cost Variance (CV) 9: Project duration (months) 10: Months that project is behind/ahead of schedule at the moment

Your project status can be presented with the diagram: What is the status of your project? Formulas: EVA Component Formula Planned value (PV) N/A Earned value (EV) N/A Actual cost (AC) N/A Budget at completion (BAC) N/A Schedule variance (SV) SV = EV – PV Cost variance (CV) CV = EV- AC Estimated final duration PlannedProjectDuration / SPI % Complete %Complete = (EV/BAC) x 100 Schedule performance index (SPI) SPI  = EV/PV Cost performance index (CPI) CPI = EV/AC Estimate at completion (EAC) – final cost Future work will be accomplished at the planned rate: Both CPI and SPI influence the remaining work: CPI is expected to be the same for the remainder of the project:   EAC = AC + BAC – EV  EAC = AC + [(BAC-EV)/(CPIxSPI)]  EAC = BAC/CPI Estimate to complete (ETC) ETC = EAC – AC Variance at Completion (VAC) VAC = BAC-EAC  

In a consumer society, many adults channel creativity into buying things

Economic stress and unpredictable times have resulted in a booming industry for self-help products

更多留学生实用工具

加入我们,立即解锁 海量真题独家解析,让复习快人一步!