4510_DESST_3514 Wk7 Lecture: Cost & Program

单项选择题

2. According to the cost influence curve, when is it most cost-effective to make design changes?

选项
A.A. During construction
B.B. During the documentation stage
C.C. During the tender process
D.D. During the concept and early design stages
查看解析

查看解析

标准答案
Please login to view
思路分析
The question asks when it is most cost-effective to make design changes according to the cost influence curve. Option A: During construction. Making changes during construction tends to be very expensive because it requires altering already-built elements, disrupting on-site work, potential rework, ......Login to view full explanation