Refer to the following network diagram. The activities (A,B,C…F) are shown in the circles and the duration for each activity is shown in weeks (Wk) next to the circles. What is the float for activity ‘C’?

查看解析
标准答案
Please login to view
思路分析
Question restatement: Refer to the network diagram. Activities A, B, C, D, E, F have durations in weeks as labeled next to each circle. What is the float for activity 'C'?
Option a: 1 week
- If C had a float of 1 week, it would mean C could be delayed by 1 week without delaying the project finish. However, C lies on the longest path from Start to Finish via A -> C -> F. Delaying C would push the overall project duration unless there is slack el......Login to view full explanation登录即可查看完整答案
我们收录了全球超50000道考试原题与详细解析,现在登录,立即获得答案。
类似问题
Question16 Which sequence of activities forms the critical path for the following project activities.Select one alternative: Start>B>D>E>H>End Start>B>C>D>E>F>G>H>I>End Start>C>F>G>I>End Start>B>C>F>G>H>I>End ResetMaximum marks: 2
Question15 You are manager of a project and after a periodic project schedule update, the scheduler working on your team comes to you with the following list of activities. He also mentions that the project is faced with 2 weeks of delay and as a corrective action he proposes to change the sequence and perform activity H concurrent with activity G, instead of after it. What would be your reaction?Select one alternative: It might affect activity I, so reject the proposal This does not have any effect on the critical path, so reject the proposal This will help all of the delay to be recovered, so accept the proposal This will help you spend less resources, so accept the proposal ResetMaximum marks: 2
Question12 How can free float be used to shorten a project schedule?Select one alternative: By delaying the tasks with free float. By finishing the tasks with free floats sooner. By assigning free floats to the tasks in critical path to put the pressure off from resources. By reallocating resources from non-critical task with free float to the concurrent tasks in critical path. ResetMaximum marks: 2
In the forward pass of the Two Pass Method, the Earliest Start Time (EST) of an activity equals the maximum of the Earliest Completion Times (ECTs) of all its immediate predecessors.