题目
单项选择题
Question16 Which sequence of activities forms the critical path for the following project activities.Select one alternative: Start>B>D>E>H>End Start>B>C>D>E>F>G>H>I>End Start>C>F>G>I>End Start>B>C>F>G>H>I>End ResetMaximum marks: 2
选项
A.Start>B>D>E>H>End
B.Start>B>C>D>E>F>G>H>I>End
C.Start>C>F>G>I>End
D.Start>B>C>F>G>H>I>End

查看解析
标准答案
Please login to view
思路分析
First, let's restate the problem in our own words to ensure understanding: We need to pick the sequence of project activities that forms the critical path from Start to End, given the start and end labels and the durations listed in the table.
Option 1: Start>B>D>E>H>End
- This path includes B (duration 4), D (duration 3), E (duration 2), and H (duration 0). Since B, D, and E have nonzero durations and there are other activities with zero slack that could extend the overall project duration, this sequence is unlikely to be the longest/critical path. Moreover, it does not pass through activitie......Login to view full explanation登录即可查看完整答案
我们收录了全球超50000道考试原题与详细解析,现在登录,立即获得答案。
类似问题
Question15 You are manager of a project and after a periodic project schedule update, the scheduler working on your team comes to you with the following list of activities. He also mentions that the project is faced with 2 weeks of delay and as a corrective action he proposes to change the sequence and perform activity H concurrent with activity G, instead of after it. What would be your reaction?Select one alternative: It might affect activity I, so reject the proposal This does not have any effect on the critical path, so reject the proposal This will help all of the delay to be recovered, so accept the proposal This will help you spend less resources, so accept the proposal ResetMaximum marks: 2
Question12 How can free float be used to shorten a project schedule?Select one alternative: By delaying the tasks with free float. By finishing the tasks with free floats sooner. By assigning free floats to the tasks in critical path to put the pressure off from resources. By reallocating resources from non-critical task with free float to the concurrent tasks in critical path. ResetMaximum marks: 2
In the forward pass of the Two Pass Method, the Earliest Start Time (EST) of an activity equals the maximum of the Earliest Completion Times (ECTs) of all its immediate predecessors.
Blank ______ path analysis is a project diagramming method used to predict total project duration.