题目
题目
单项选择题

Question16 Which sequence of activities forms the critical path for the following project activities.Select one alternative: Start>B>D>E>H>End Start>B>C>D>E>F>G>H>I>End Start>C>F>G>I>End Start>B>C>F>G>H>I>End ResetMaximum marks: 2

选项
A.Start>B>D>E>H>End
B.Start>B>C>D>E>F>G>H>I>End
C.Start>C>F>G>I>End
D.Start>B>C>F>G>H>I>End
题目图片
查看解析

查看解析

标准答案
Please login to view
思路分析
First, let's restate the problem in our own words to ensure understanding: We need to pick the sequence of project activities that forms the critical path from Start to End, given the start and end labels and the durations listed in the table. Option 1: Start>B>D>E>H>End - This path includes B (duration 4), D (duration 3), E (duration 2), and H (duration 0). Since B, D, and E have nonzero durations and there are other activities with zero slack that could extend the overall project duration, this sequence is unlikely to be the longest/critical path. Moreover, it does not pass through activitie......Login to view full explanation

登录即可查看完整答案

我们收录了全球超50000道考试原题与详细解析,现在登录,立即获得答案。

类似问题

更多留学生实用工具

加入我们,立即解锁 海量真题独家解析,让复习快人一步!