Question15 You are manager of a project and after a periodic project schedule update, the scheduler working on your team comes to you with the following list of activities. He also mentions that the project is faced with 2 weeks of delay and as a corrective action he proposes to change the sequence and perform activity H concurrent with activity G, instead of after it. What would be your reaction?Select one alternative: It might affect activity I, so reject the proposal This does not have any effect on the critical path, so reject the proposal This will help all of the delay to be recovered, so accept the proposal This will help you spend less resources, so accept the proposal ResetMaximum marks: 2

选项
A.It might affect activity I, so reject the proposal
B.This does not have any effect on the critical path, so reject the proposal
C.This will help all of the delay to be recovered, so accept the proposal
D.This will help you spend less resources, so accept the proposal
题目图片
查看解析

查看解析

标准答案
Please login to view
思路分析
To tackle this question, I’ll walk through each option and evaluate its claim in the context of project scheduling and critical path concepts. Option 1: 'It might affect activity I, so reject the proposal' This option suggests that changing the sequence by running H concurrently with G could impact activity I. Without a detailed network diagram showing dependencies, it’s risky to assume I is affected. If I is not on the critical path or if its predecessors aren’t constrained by G or H in a way that creates a delay, the impact may be limited. However, the statement is speculative and asserts a def......Login to view full explanation

登录即可查看完整答案

我们收录了全球超50000道考试原题与详细解析,现在登录,立即获得答案。

类似问题

更多留学生实用工具

加入我们,立即解锁 海量真题独家解析,让复习快人一步!