Question12 How can free float be used to shorten a project schedule?Select one alternative: By delaying the tasks with free float. By finishing the tasks with free floats sooner. By assigning free floats to the tasks in critical path to put the pressure off from resources. By reallocating resources from non-critical task with free float to the concurrent tasks in critical path. ResetMaximum marks: 2

选项
A.By delaying the tasks with free float.
B.By finishing the tasks with free floats sooner.
C.By assigning free floats to the tasks in critical path to put the pressure off from resources.
D.By reallocating resources from non-critical task with free float to the concurrent tasks in critical path.
查看解析

查看解析

标准答案
Please login to view
思路分析
Question restatement: The prompt asks how free float can be used to shorten a project schedule, selecting the correct alternative. Option 1: By delaying the tasks with free float. This is not a method to shorten the overall project duration. Free float represents the amount of time a non-critical task can be delayed without impacting the project end date, but delaying these tasks does not compress th......Login to view full explanation

登录即可查看完整答案

我们收录了全球超50000道考试原题与详细解析,现在登录,立即获得答案。

类似问题

更多留学生实用工具

加入我们,立即解锁 海量真题独家解析,让复习快人一步!