题目
单项选择题
Question12 How can free float be used to shorten a project schedule?Select one alternative: By delaying the tasks with free float. By finishing the tasks with free floats sooner. By assigning free floats to the tasks in critical path to put the pressure off from resources. By reallocating resources from non-critical task with free float to the concurrent tasks in critical path. ResetMaximum marks: 2
选项
A.By delaying the tasks with free float.
B.By finishing the tasks with free floats sooner.
C.By assigning free floats to the tasks in critical path to put the pressure off from resources.
D.By reallocating resources from non-critical task with free float to the concurrent tasks in critical path.
查看解析
标准答案
Please login to view
思路分析
Question restatement: The prompt asks how free float can be used to shorten a project schedule, selecting the correct alternative.
Option 1: By delaying the tasks with free float. This is not a method to shorten the overall project duration. Free float represents the amount of time a non-critical task can be delayed without impacting the project end date, but delaying these tasks does not compress th......Login to view full explanation登录即可查看完整答案
我们收录了全球超50000道考试原题与详细解析,现在登录,立即获得答案。
类似问题
Question16 Which sequence of activities forms the critical path for the following project activities.Select one alternative: Start>B>D>E>H>End Start>B>C>D>E>F>G>H>I>End Start>C>F>G>I>End Start>B>C>F>G>H>I>End ResetMaximum marks: 2
Question15 You are manager of a project and after a periodic project schedule update, the scheduler working on your team comes to you with the following list of activities. He also mentions that the project is faced with 2 weeks of delay and as a corrective action he proposes to change the sequence and perform activity H concurrent with activity G, instead of after it. What would be your reaction?Select one alternative: It might affect activity I, so reject the proposal This does not have any effect on the critical path, so reject the proposal This will help all of the delay to be recovered, so accept the proposal This will help you spend less resources, so accept the proposal ResetMaximum marks: 2
In the forward pass of the Two Pass Method, the Earliest Start Time (EST) of an activity equals the maximum of the Earliest Completion Times (ECTs) of all its immediate predecessors.
Blank ______ path analysis is a project diagramming method used to predict total project duration.
更多留学生实用工具
希望你的学习变得更简单
加入我们,立即解锁 海量真题 与 独家解析,让复习快人一步!