In the forward pass of the Two Pass Method, the Earliest Start Time (EST) of an activity equals the maximum of the Earliest Completion Times (ECTs) of all its immediate predecessors.

选项
A.True
B.False
查看解析

查看解析

标准答案
Please login to view
思路分析
In this question, we’re examining the forward pass of the Two Pass Method used in project scheduling. Option 1: True. The statement says the Earliest Start Time (EST) of an activity equals the maximum of the Earliest Completion Times (ECTs) of all its immediate predecessors. This aligns with the sta......Login to view full explanation