题目
题目
单项选择题

Blank ______ path analysis is a project diagramming method used to predict total project duration.

选项
A.Dependency
B.PERT
C.Critical
D.Gantt
查看解析

查看解析

标准答案
Please login to view
思路分析
The question presents a fill-in where a specific project management concept is described: a diagramming method used to predict total project duration. Option 1: Dependency. While dependencies between tasks exist in project diagrams, simply noting that tasks depend on one another does not by itself provide a method for predicting total duration. It’s a relational detail rather th......Login to view full explanation

登录即可查看完整答案

我们收录了全球超50000道考试原题与详细解析,现在登录,立即获得答案。

类似问题

Question16 Which sequence of activities forms the critical path for the following project activities.Select one alternative: Start>B>D>E>H>End Start>B>C>D>E>F>G>H>I>End Start>C>F>G>I>End Start>B>C>F>G>H>I>End ResetMaximum marks: 2

Question15 You are manager of a project and after a periodic project schedule update, the scheduler working on your team comes to you with the following list of activities. He also mentions that the project is faced with 2 weeks of delay and as a corrective action he proposes to change the sequence and perform activity H concurrent with activity G, instead of after it. What would be your reaction?Select one alternative: It might affect activity I, so reject the proposal This does not have any effect on the critical path, so reject the proposal This will help all of the delay to be recovered, so accept the proposal This will help you spend less resources, so accept the proposal ResetMaximum marks: 2

Question12 How can free float be used to shorten a project schedule?Select one alternative: By delaying the tasks with free float. By finishing the tasks with free floats sooner. By assigning free floats to the tasks in critical path to put the pressure off from resources. By reallocating resources from non-critical task with free float to the concurrent tasks in critical path. ResetMaximum marks: 2

In the forward pass of the Two Pass Method, the Earliest Start Time (EST) of an activity equals the maximum of the Earliest Completion Times (ECTs) of all its immediate predecessors.

更多留学生实用工具

加入我们,立即解锁 海量真题独家解析,让复习快人一步!