SCHM2301.60549.202560 Assessment Survey

单项选择题

A process consists of five machines producing a metal part. The parts move in sequence from Machine 1 to Machine 5. Processing at Machine 1 takes 10 seconds then the parts move to Machine 2 where processing takes 15 seconds. In Machine 3, the processing takes 12 seconds and in Machine 4, the processing takes 20 seconds. The parts finally move to Machine 5 where processing takes 18 seconds.  Which machine in this process is the bottleneck machine? 

选项
A.Machine 1
B.Machine 2
C.Machine 3
D.Machine 4
E.Machine 5
查看解析

查看解析

标准答案
Please login to view
思路分析
To identify the bottleneck in a sequential flow, we compare the processing times at each machine, since the bottleneck is the station that takes the longest to process a part and thus limits the overall throughput. Option: Machine 1 - Processing time at Machine 1 is 10 seconds. This is relatively short compared to oth......Login to view full explanation

登录即可查看完整答案

我们收录了全球超50000道考试原题与详细解析,现在登录,立即获得答案。

更多留学生实用工具

加入我们,立即解锁 海量真题独家解析,让复习快人一步!