题目
题目
单项选择题

One valuation method is the Adjusted Present Value (APV) method. Which statement regarding the APV method is most likely wrong?

选项
A.A. The APV method is appropriate if the amount of debt is not constant over time.
B.B. The tax shield is considered in the unlevered cash flows.
C.C. The APV method splits the entity value of a debt financed firm into the value of a unlevered firm and the present value of the tax shield
D.D. Assuming a constant debt level, the tax shield has the same risk as debt
查看解析

查看解析

标准答案
Please login to view
思路分析
Examining the APV (Adjusted Present Value) framework and what each statement implies about its mechanics helps identify the incorrect option. Option A: 'The APV method is appropriate if the amount of debt is not constant over time.' In APV, we can value the unlevered (all-equity) firm and then separately add the present value of financing effects such as the tax shield. This approach is particularly convenient when debt levels are changing over t......Login to view full explanation

登录即可查看完整答案

我们收录了全球超50000道考试原题与详细解析,现在登录,立即获得答案。

类似问题

The Mars project will generate a free cash flow of $110 per year forever starting in Year 1 and its unlevered cost of capital is 20%. The project costs $400 and it will be financed entirely with a loan with the following fixed schedule: borrow $400 today, pay annual interest on the principal at a 10% rate in Year 1 and Year 2, and repay the principal at the end of Year 2. The tax rate is 40%. The project’s NPV estimated using the APV method (with one decimal) is:

Continuing on from Question 3: Abacus Industries is considering a 3-year project that will cost $200 today followed by free cash flows to the firm of $100 in year 1, $80 in year 2, and $160 in year 3. The tax rate is 35%.  Assuming instead of 100% equity, Abacus funds the project with $70 of debt at an interest rate of 7%. For the three years of the project ABC will pay only interest. The loan of $70 will be repaid at the end of year 3. The balance of the cost of the project will be financed with equity. What is the levered NPV of this project using the APV method:

Continuing on from Question 1: ABC is still considering investing in the project with the initial cost of $560,000 and that will earn unlevered free cash flows (FCFF) of $96,000 per year in perpetuity. The unlevered cost of capital is still 20% and the tax rate is 40%. Assume instead of funding with 100% equity, ABC funds the project with $280,000 in perpetual debt (wtih an interest rate of 10%) and the remainder of funding will be with equity.  What is the NPV of the levered project using the APV method?

One valuation method is the Adjusted Present Value (APV) method. Which statement regarding the APV method is most likely wrong?

更多留学生实用工具

加入我们,立即解锁 海量真题独家解析,让复习快人一步!