题目
MGT232H5 F LEC0101
单项选择题
Continuing on from Question 3: Abacus Industries is considering a 3-year project that will cost $200 today followed by free cash flows to the firm of $100 in year 1, $80 in year 2, and $160 in year 3. The tax rate is 35%. Assuming instead of 100% equity, Abacus funds the project with $70 of debt at an interest rate of 7%. For the three years of the project ABC will pay only interest. The loan of $70 will be repaid at the end of year 3. The balance of the cost of the project will be financed with equity. What is the levered NPV of this project using the APV method:
选项
A.$79.10
查看解析
标准答案
Please login to view
思路分析
Question restatement:
- Project: 3-year project costing $200 today, with free cash flows to the firm (FCFF) of $100 in year 1, $80 in year 2, and $160 in year 3. Tax rate = 35%.
- Financing: Instead of 100% equity, the project is financed with $70 of debt at 7% interest. For the three years, the project pays only interest. The $70 debt is repaid at the end of year 3. The remaining cost of the project is financed with equity. Compute the levered NPV (APV method).
- Answer options: "$79.10".
Step-by-step analysis of each option:
Option presented: "$79.10".
- First, understand the APV framework in this financing setup. APV separates two components: (a) the NPV of the project as if financed entirely with equity (unlevered NPV), using FCFF and the project’s cost of equity (or discount rate for the unlev......Login to view full explanation登录即可查看完整答案
我们收录了全球超50000道考试原题与详细解析,现在登录,立即获得答案。
类似问题
The Mars project will generate a free cash flow of $110 per year forever starting in Year 1 and its unlevered cost of capital is 20%. The project costs $400 and it will be financed entirely with a loan with the following fixed schedule: borrow $400 today, pay annual interest on the principal at a 10% rate in Year 1 and Year 2, and repay the principal at the end of Year 2. The tax rate is 40%. The project’s NPV estimated using the APV method (with one decimal) is:
Continuing on from Question 1: ABC is still considering investing in the project with the initial cost of $560,000 and that will earn unlevered free cash flows (FCFF) of $96,000 per year in perpetuity. The unlevered cost of capital is still 20% and the tax rate is 40%. Assume instead of funding with 100% equity, ABC funds the project with $280,000 in perpetual debt (wtih an interest rate of 10%) and the remainder of funding will be with equity. What is the NPV of the levered project using the APV method?
One valuation method is the Adjusted Present Value (APV) method. Which statement regarding the APV method is most likely wrong?
One valuation method is the Adjusted Present Value (APV) method. Which statement regarding the APV method is most likely wrong?
更多留学生实用工具
希望你的学习变得更简单
加入我们,立即解锁 海量真题 与 独家解析,让复习快人一步!