The term “roll-up” in a WBS context refers to:

Options
A.Breaking tasks into smaller subtasks
B.Reviewing activities for float
C.Combining detailed elements into higher-level summaries
D.Adjusting the cost estimate for escalation
View Explanation

View Explanation

Verified Answer
Please login to view
Step-by-Step Analysis
To understand the term 'roll-up' in a Work Breakdown Structure (WBS) context, we need to consider how WBS organizes work. Option 1: 'Breaking tasks into smaller subtasks' describes decomposition, not roll-up. Decomposition......Login to view full explanation