Questions
Homework:Ch 08 Homework
Single choice
Part 1Which is the best statement regarding work breakdown structure?Part 2 A. A packet is the smallest unit of work effort consuming both time and resources that the project manager can schedule and control. B. WBS should not include a task representing planning of the project that is being planned. C. Each activity in the WBS must have an "owner" who is responsible for doing the work. D. A Level 1 activity is a more micro view (greater level of detail) than a Level 2 activity.
Options
A.A. A packet is the smallest unit of work effort consuming both time and resources that the project manager can schedule and control.
B.B. WBS should not include a task representing planning of the project that is being planned.
C.C. Each activity in the WBS must have an "owner" who is responsible for doing the work.
D.D. A Level 1 activity is a more micro view (greater level of detail) than a Level 2 activity.
View Explanation
Verified Answer
Please login to view
Step-by-Step Analysis
In evaluating the statements about the work breakdown structure (WBS), I’ll consider what each option implies about standard PM practice and foundational concepts.
Option A: 'A packet is the smallest unit of work effort consuming both time and resources that the project manager can schedule and control.' The term here is likely a misspelling of 'work package,' which is indeed the lowest level in a WBS. A work package is the smallest unit that can be scheduled, costed, and assigned, and it represents a discrete scope of work. This makes the statement largely c......Login to view full explanationLog in for full answers
We've collected over 50,000 authentic exam questions and detailed explanations from around the globe. Log in now and get instant access to the answers!
Similar Questions
Question17 What is the main purpose of creating a work breakdown structure (WBS) in project management?Select one alternative: To identify and categorize all the risks and opportunities associated with project execution. To outline the sequence of tasks in the project and determine the critical path for completion. To identify missing stakeholders To break the project into smaller, manageable components that can be planned, tracked, and executed effectively. ResetMaximum marks: 2
Question17 What is the main purpose of creating a work breakdown structure (WBS) in project management?Select one alternative: To outline the sequence of tasks in the project and determine the critical path for completion. To break the project into smaller, manageable components that can be planned, tracked, and executed effectively. To identify and categorize all the risks and opportunities associated with project execution. To identify missing stakeholders ResetMaximum marks: 2
The team lists major deliverables, breaks them into smaller tasks, and assigns each to specific departments. Which project tool supports this process?
During the execution phase of a project, your team loses some key resources. There are a few deadlines to be met within the next three months and there are fortnightly update meetings with the client. A few new people are hired and you as the project manager need to set up a meeting to get the team working together on the project. What should be the main focus of this meeting?
More Practical Tools for Students Powered by AI Study Helper
Making Your Study Simpler
Join us and instantly unlock extensive past papers & exclusive solutions to get a head start on your studies!