Homework:Ch 08 Homework

Single choice

Part 1Which is the best statement regarding work breakdown​ structure?Part 2 A. A packet is the smallest unit of work effort consuming both time and resources that the project manager can schedule and control. B. WBS should not include a task representing planning of the project that is being planned. C. Each activity in the WBS must have an​ "owner" who is responsible for doing the work. D. A Level 1 activity is a more micro view​ (greater level of​ detail) than a Level 2 activity.

Options
A.A. A packet is the smallest unit of work effort consuming both time and resources that the project manager can schedule and control.
B.B. WBS should not include a task representing planning of the project that is being planned.
C.C. Each activity in the WBS must have an ​ "owner" who is responsible for doing the work.
D.D. A Level 1 activity is a more micro view ​ (greater level of ​ detail) than a Level 2 activity.
View Explanation

View Explanation

Verified Answer
Please login to view
Step-by-Step Analysis
In evaluating the statements about the work breakdown structure (WBS), I’ll consider what each option implies about standard PM practice and foundational concepts. Option A: 'A packet is the smallest unit of work effort consuming both time and resources that the project manager can schedule and control.' The term here is likely a misspelling of 'work package,' which is indeed the lowest level in a WBS. A work package is the smallest unit that can be scheduled, costed, and assigned, and it represents a discrete scope of work. This makes the statement largely c......Login to view full explanation

Log in for full answers

We've collected over 50,000 authentic exam questions and detailed explanations from around the globe. Log in now and get instant access to the answers!

Similar Questions

More Practical Tools for Students Powered by AI Study Helper

Join us and instantly unlock extensive past papers & exclusive solutions to get a head start on your studies!