MGF5903 - S2 2025 Week 1-8 Quiz (20%)
Single choice
Scenario: A metropolitan authority is delivering a megaproject to build a new airport. The project manager has successfully engaged with airlines and government regulators. However, a coalition of local community groups has emerged, citing concerns over noise pollution and environmental impact. They are politically well-connected and have significant coercive power. The project team's initial approach was to present technical data showing minimal impact, which was dismissed by the groups as corporate propaganda.Question: According to the stakeholder engagement model by Erkul et al. (2020), which stakeholder effective attribute has the project team most critically misjudged?

View Explanation
Verified Answer
Please login to view
Step-by-Step Analysis
The scenario describes a megaproject where a coalition of locally powerful community groups is opposing the project due to noise and environmental concerns. The project team initially relied on technical data to make their case, but this was dismissed by the community groups as propaganda. The question asks, according to the stakeholder engagement model by Erkul et al. (2020), which stakeholder effective attribute the team misjudged most.
First, it's important to restate what the available material provides about the correct choice: the provided correct option text identifies the misjudged attribute as 'Relationship Network & Power' and notes that the team underestimated the stakeholders' abi......Login to view full explanationLog in for full answers
We've collected over 50,000 authentic exam questions and detailed explanations from around the globe. Log in now and get instant access to the answers!
Similar Questions
Question9 For the purpose of recording project lessons learned, you are analyzing the major delay in the project schedule. The root cause of the delay was a demonstration done by a group of green initiative supporters. They were unhappy because their representatives were not informed about all of the arrangements that you are taking to protect the environment. What could you and your team have done better to prevent this from happening?Select one alternative: A clearer communication management plan A more accurate risk response planning A better project management plan A more accurate stakeholder identification and engagement ResetMaximum marks: 1
Question 29 Choose one option. Who should be included in discussions about SMART design?
What example does the McKinset article author provide to illustrate a company engaging Gen Z stakeholders directly in its sustainability strategy?
What role does social media play in stakeholder engagement?