Question9 For the purpose of recording project lessons learned, you are analyzing the major delay in the project schedule. The root cause of the delay was a demonstration done by a group of green initiative supporters. They were unhappy because their representatives were not informed about all of the arrangements that you are taking to protect the environment. What could you and your team have done better to prevent this from happening?Select one alternative: A clearer communication management plan A more accurate risk response planning A better project management plan A more accurate stakeholder identification and engagement ResetMaximum marks: 1

Options
A.A clearer communication management plan
B.A more accurate risk response planning
C.A better project management plan
D.A more accurate stakeholder identification and engagement
View Explanation

View Explanation

Verified Answer
Please login to view
Step-by-Step Analysis
The question asks what the team could have done better to prevent a stakeholder-related disruption in a project, specifically involving green initiative supporters whose representatives felt uninformed about environmental protections. Option 1: 'A clearer communication management plan' — While a clearer communication plan helps ensure messages are delivered, it focuses on the mechanics of communication rather than who needs to be......Login to view full explanation

Log in for full answers

We've collected over 50,000 authentic exam questions and detailed explanations from around the globe. Log in now and get instant access to the answers!

Similar Questions

More Practical Tools for Students Powered by AI Study Helper

Join us and instantly unlock extensive past papers & exclusive solutions to get a head start on your studies!