PMGT5887 (all) Weekly Quiz 7
Single choice
You have overallocated a resource in Microsoft Project. Which feature allows you to adjust the workload distribution without changing the project end date?
Options
A.Baseline Reset
B.Work Breakdown Structure
C.Contour Adjustment
D.Resource Leveling
View Explanation
Verified Answer
Please login to view
Step-by-Step Analysis
The question asks about adjusting workload distribution in Microsoft Project without altering the overall project end date when a resource is overallocated.
Option 1: Baseline Reset. This would revert the project to its original baseline; it does not directly address the issue of redistributing workload or resolving overallocations, and it could affect the p......Login to view full explanationLog in for full answers
We've collected over 50,000 authentic exam questions and detailed explanations from around the globe. Log in now and get instant access to the answers!
Similar Questions
In a consumer society, many adults channel creativity into buying things
Economic stress and unpredictable times have resulted in a booming industry for self-help products
People born without creativity never can develop it
A product has a selling price of $20, a contribution margin ratio of 40% and fixed cost of $120,000. To make a profit of $30,000. The number of units that must be sold is: Type the number without $ and a comma. Eg: 20000
More Practical Tools for Students Powered by AI Study Helper
Making Your Study Simpler
Join us and instantly unlock extensive past papers & exclusive solutions to get a head start on your studies!